The Hook Lab / Tracker / North America / United States / PowerHouse ABX-1
Updated 2026-11-25
Tracker · United States · PJM · VA
PowerHouse ABX-1
PowerHouse Data Centers · Ashburn, VA
Under constructionchanged 2024-12-31
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Ashburn, VA
- Network
- —
- Construction started
- 2022-09
- First reported by
- PowerHouse · no status given
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
- ≤ 2024-12-31on or before
-
2022-09
stageUnder construction1 source
- dpr.com press
The project broke ground in September 2022 and reached completion in October 2023.
- dpr.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.