Updated 2026-11-25
Tracker · United States · MISO · MN
Oppidan North Mankato data centre
Oppidan · North Mankato, MN
Pausedplanning approvalstage not on recordchanged 2025-11-17
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- United States · North America
- Grid
- MISO · MISO
- Place
- North Mankato, MN
- Network
- —
- First reported by
- Star Tribune · paused
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-11-17date: document dateon or before
conditionPaused1 sourceplanning approval
- mankatofreepress.com press
The Excelsior-based company paused work on data center projects in North Mankato and in Hampton, citing concerns about the time required for the state to permit backup generators
- mankatofreepress.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.