NTT Gainesville campus
NTT Global Data Centers · Near I-66 and Route 29, Gainesville, Prince William County, VA
Planning approvedchanged 2025-12-02
336 MWrequested
—offered
—energised
59 mowaiting since first filing
mediumconfidence · 4 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Near I-66 and Route 29, Gainesville, Prince William County, VA
- Network
- —
- Announced
- 2022-06-14
- Planning lodged
- 2021-12-31
- Planning approved
- 2021-12
- First reported by
- Data Center Frontier · approved
- Dates it gives
- rezoning and SUP approved 2021-12-07 (DCD, county FAQ)
land bought from Lerner, plan reported 2022-06-14
first building due 2024-Q2
Timeline
20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-12-02date: document dateon or before
milestoneOwnership changed1 source
- princewilliamtimes.com press
Six months later, Lerner Enterprises sold the property to NTT for $257 million, about $2.5 million an acre.
- princewilliamtimes.com press
-
2022-06-14
stageAnnounced1 source
- Data Center Frontier press
NTT has acquired property from Lerner Enterprises in Gainesville, Va. where it plans to develop 2 million square feet of data center space, supporting 336 megawatts (MWs) of capacity.
- Data Center Frontier press
-
≤ 2021-12-31on or before
stagePlanning lodged1 source
- princewilliamtimes.com press
In 2021, its owner, Lerner Enterprises, sought a rezoning and changes to its development restrictions.
- princewilliamtimes.com press
-
2021-12
stagePlanning approved1 source
- princewilliamtimes.com press
In December 2021, the supervisors approved the project.
- princewilliamtimes.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.