The Hook Lab / Tracker / North America / United States / NTT Ashburn VA3 Updated 2026-11-25
Tracker · United States · PJM · VA

NTT Ashburn VA3

NTT Data Group · 44245 Gigabit Plaza, Ashburn, VA

Under constructionchanged 2016-12
16 MWrequested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
Market
United States · North America
Grid
PJM · PJM
Place
44245 Gigabit Plaza, Ashburn, VA
Network
—
Construction started
2016-12
First reported by
NTT DATA · no status given

Who is on it

Developer
NTT Communications · sec.gov
Owner
NTT · askthegrid.com

Timeline

2016201820202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2016-12
    stageUnder constructionconfirmed
    • sec.gov primary
      NTT Com also commenced the construction of the Virginia Ashburn 3 (VA3) Data Center in December 2016.
    • sec.gov primary
      NTT Group began construction on its Virginia Ashburn 3 (VA3) Data Center, designed to achieve strong security and high-level energy savings
    • sec.gov primary
      we began construction on our “Virginia Ashburn 3 (VA3) Data center,” designed to achieve strong security and high-level energy savings

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.