The Hook Lab / Tracker / North America / United States / Novva Tahoe Reno
Updated 2026-11-25
Tracker · United States · NV
Novva Tahoe Reno
Novva Data Centers · Tahoe Reno, NV
Announcedchanged 2026-01-13
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Tahoe Reno, NV
- Network
- —
- Announced
- 2026-01-13
- First reported by
- Novva · no status given
Who is on it
- Owner
- Novva Data Centers · novva.com
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-01-13date: document dateon or before
stageAnnouncedconfirmed
- Novva primary
Novva Data Centers, a state-of-the-art data center company providing purpose-built data center facilities, announces the launch of its 300,000 square foot, 60 MW data center in Storey County, Nevada.
- Novva primary
-
≤ 2022-12-31on or before
milestoneOwnership changedconfirmed
- Novva primary
Since acquiring the property in 2022, the launch of Novva Tahoe Reno becomes Novva’s fourth completed data center location alongside existing facilities in Colorado Springs, Colorado, West Jordan, Utah and North Las Vegas, Nevada.
- prnewswire.com press
Since acquiring the property in 2022
- Novva primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.