Novva Data Centers · Tahoe Reno, NV

Announcedchanged 2026-01-13
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
Market
United States · North America
Grid
not settled yet
Place
Tahoe Reno, NV
Network
—
Announced
2026-01-13
First reported by
Novva · no status given

Who is on it

Owner
Novva Data Centers · novva.com

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-01-13date: document dateon or before
    stageAnnouncedconfirmed
    • Novva primary
      Novva Data Centers, a state-of-the-art data center company providing purpose-built data center facilities, announces the launch of its 300,000 square foot, 60 MW data center in Storey County, Nevada.
  2. ≤ 2022-12-31on or before
    milestoneOwnership changedconfirmed
    • Novva primary
      Since acquiring the property in 2022, the launch of Novva Tahoe Reno becomes Novva’s fourth completed data center location alongside existing facilities in Colorado Springs, Colorado, West Jordan, Utah and North Las Vegas, Nevada.
    • prnewswire.com press
      Since acquiring the property in 2022

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.