The Hook Lab / Tracker / North America / United States / New Hill Digital Campus Updated 2026-11-25
Tracker · United States · US-OTHER · NC

New Hill Digital Campus

Natelli Investments · Apex, NC

Cancelledwithdrawn by proponentstage not on recordchanged 2026-03-12
—requested
—offered
—energised
—closed
mediumconfidence · 3 sources
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Apex, NC
Network
—
First reported by
DCD · cancelled

Who is on it

Developer
Natelli Investments LLC · datacenterdynamics.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-03-12date: document dateon or before
    conditionCancelled1 sourcewithdrawn by proponent
    • hoodline.com press
      Natelli Investments announced it was withdrawing its annexation and rezoning applications for the New Hill Digital Campus, effectively halting the project for the moment
  2. ≤ 2026-03-12date: document dateon or before
    conditionContestedconfirmedcommunity opposition
    • hoodline.com press
      Opponents rallied under the banner of the Protect Wake County Coalition and launched a Change.org petition that has collected roughly 4,700 signatures against the project.
    • DCD press
      But fierce opposition from residents and the local government has led the company to back out on Thursday, according to several reports and a statement issued by Apex's Mayor Pro Tempore Terry Mahaffey on his Substack.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error