Nebius · Kansas City, MO

Announcedchanged 2024-11-19
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
Kansas City, MO
Network
—
Announced
2024-11-19
First reported by
Nebius · operating · opened 2025
Dates it gives
announced 2024-11-19
launched 2025-04

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2024-11-19
    stageAnnouncedconfirmed
    • Nebius primary
      today announced the launch of its first NVIDIA GPU cluster in the United States with a deployment in Kansas City, MO, bringing its AI-native cloud closer to American customers.
    • sec.gov primary
      Amsterdam, November 19, 2024 — Nebius Group N.V. (“Nebius Group”, “Nebius” or the “Company”; NASDAQ:NBIS), a leading AI infrastructure company, today announced the launch of its first GPU cluster in the United States with a deployment in Kansas City, MO, bringing its AI-native cloud closer to American customers.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.