The Hook Lab / Tracker / North America / United States / Microsoft Gaines Charter Township datacenter Updated 2026-11-25
Tracker · United States · MISO · MI

Microsoft Gaines Charter Township datacenter

Microsoft · Gaines Charter Township, MI

Planning lodgedchanged 2026-04-09
—requested
—offered
—energised
8 mowaiting since first filing
lowconfidence · 1 source
Market
United States · North America
Grid
MISO · MISO
Place
Gaines Charter Township, MI
Network
—
Planning lodged
2026-04-09
First reported by
Microsoft · planned

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-04-09date: document dateon or before
    stagePlanning lodged1 source
    • wwmt.com press
      Microsoft submitted a request to rezone 40.5 acres of property, located on Patterson Avenue, from "large-scale planned unit development" to "light industrial."

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.