The Hook Lab / Tracker / North America / United States / Meta Tulsa Data Center Updated 2026-11-25
Tracker · United States · OK

Meta Tulsa Data Center

Meta · Tulsa, OK

Under constructionchanged 2026-04-21
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
Market
United States · North America
Grid
not settled yet
Place
Tulsa, OK
Network
—
Announced
2026-04-21
Construction started
2026-04-21
First reported by
Meta · no status given
Dates it gives
broke ground 2026

Who is on it

Builder
Fortis Construction · okcommerce.gov

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-04-21
    stageAnnouncedconfirmed
    • okcommerce.gov primary
      We’re proud to call Tulsa home as we announce Meta’s first data center in Oklahoma.
    • Meta primary
      Tulsa, Oklahoma, will be home to our next AI data center
  2. 2026-04-21
    stageUnder constructionconfirmed
    • okcommerce.gov primary
      Today, local and state leaders joined Meta to break ground on the company’s newest data center in Tulsa, representing an investment of more than $1 billion and marking one of the largest economic development projects in the region’s history.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.