The Hook Lab / Tracker / North America / United States / Meta Prineville Data Center Updated 2026-11-25
Tracker · United States · US-OTHER · OR

Meta Prineville Data Center

Meta · Prineville, OR

Under constructionchanged 2010-12-31
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Prineville, OR
Network
—
Construction started
2010-12-31
First reported by
Meta · no status given
Dates it gives
broke ground 2010

Who is on it

Builder
DPR Construction · dpr.com
Owner
Meta · datacenters.atmeta.com

Timeline

200820122016202020242028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2010-12-31on or before
    stageUnder constructionconfirmed
    • Meta primary
      Broke ground on the Prineville Data Center

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.