The Hook Lab / Tracker / North America / United States / Meta Bowling Green Data Center
Updated 2026-11-25
Tracker · United States · PJM · OH
Meta Bowling Green Data Center
Meta · Bowling Green, OH
Under constructionchanged 2025-11-24
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Bowling Green, OH
- Network
- —
- Announced
- 2025-04-09
- Construction started
- 2025-11-24
- First reported by
- Meta · no status given
- Dates it gives
- broke ground 2025
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-11-24date: document dateon or before
stageUnder construction1 source
- jobsohio.com press
Construction has already started and is expected to last for several years.
- jobsohio.com press
-
2025-04-09
stageAnnounced1 source
- jobsohio.com press
The Regional Growth Partnership (RPG) and JobsOhio announced today that Meta will be building its newest AI-optimized data center in Northwest Ohio.
- jobsohio.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.