The Hook Lab / Tracker / North America / United States / MD Squared Pikeville data centre Updated 2026-11-25
Tracker · United States · PJM · KY

MD Squared Pikeville data centre

MD Squared · Pikeville, Pike County, KY

Announcedchanged 2026-06-05
30 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
PJM · PJM
Place
Pikeville, Pike County, KY
Network
—
Announced
2026-06-05
First reported by
States Newsroom · planned

Who is on it

Developer
MD Squared · newsfromthestates.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-06-05
    stageAnnouncedconfirmed
    • servercountry.org press
      Pikeville signed a preliminary agreement with MD Squared Power LLC to explore a potential data center at the Kentucky Enterprise Industrial Park.
    • States Newsroom press
      The Lexington Herald-Leader reported on June 5 the city of Pikeville had entered into a preliminary agreement with data center developer MD Squared to explore building a $250 million, 25 to 30 megawatt data center in an industrial park.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error