The Hook Lab / Tracker / North America / United States / Madison Heights data centre
Updated 2026-11-25
Tracker · United States · PJM · VA
Madison Heights data centre
Old Dominion Capital Partners LLC · US 29 Business north of Seminole Plaza, Madison Heights, Amherst County, VA
Planning lodgedchanged 2026-08-31
—requested
—offered
—energised
≥ 3 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- US 29 Business north of Seminole Plaza, Madison Heights, Amherst County, VA
- Network
- —
- Planning lodged
- 2026-08-31
- First reported by
- Cardinal News · application lodged
- Dates it gives
- site plan submitted 2026-08, deemed incomplete around 2026-09-21
Who is on it
- Developer
- Old Dominion Capital Partners LLC · wset.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-08-31date: document dateon or before
stagePlanning lodgedconfirmed
- wset.com press
The developer filed its application on Aug. 18 — the same day the Amherst County Board of Supervisors voted to change the county's zoning rules for data centers.
- Cardinal News press
In August, Amherst County received a site plan from Old Dominion Capital Partners LLC for a data center on about 90 acres of land zoned for industrial use in Madison Heights.
- wset.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.