The Hook Lab / Tracker / North America / United States / Madison Heights data centre Updated 2026-11-25
Tracker · United States · PJM · VA

Madison Heights data centre

Old Dominion Capital Partners LLC · US 29 Business north of Seminole Plaza, Madison Heights, Amherst County, VA

Planning lodgedchanged 2026-08-31
—requested
—offered
—energised
≥ 3 mowaiting since first filing
mediumconfidence · 2 sources
Market
United States · North America
Grid
PJM · PJM
Place
US 29 Business north of Seminole Plaza, Madison Heights, Amherst County, VA
Network
—
Planning lodged
2026-08-31
First reported by
Cardinal News · application lodged
Dates it gives
site plan submitted 2026-08, deemed incomplete around 2026-09-21

Who is on it

Developer
Old Dominion Capital Partners LLC · wset.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-08-31date: document dateon or before
    stagePlanning lodgedconfirmed
    • wset.com press
      The developer filed its application on Aug. 18 — the same day the Amherst County Board of Supervisors voted to change the county's zoning rules for data centers.
    • Cardinal News press
      In August, Amherst County received a site plan from Old Dominion Capital Partners LLC for a data center on about 90 acres of land zoned for industrial use in Madison Heights.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.