Updated 2026-11-25
Tracker · United States · PJM · PA
Klondike data centre
KDI Wyalusing Power LLC · Wyalusing Township, Bradford County, PA
Planning approvedchanged 2025-10-09
—requested
—offered
—energised
24 mowaiting since first filing
mediumconfidence · 4 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Wyalusing Township, Bradford County, PA
- Network
- —
- Planning lodged
- 2024-12
- Planning approved
- 2025-10-09
- Planning lodged → approved
- 10 mo
- First reported by
- files.dep.state.pa.us · planned
- Dates it gives
- power plant application 2024-12-26
DEP air plan approval 2025-10-09
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-10-09
stagePlanning approvedconfirmed
- files.dep.state.pa.us press
Therefore, the Department decided to issue the plan approval (No. 08-00060A) for the Application to KDI Wyalusing Power LLC on October 9, 2025.
- compute-atlas.com press
PA DEP issued an air quality plan approval for the Wyalusing Energy Center — eight natural gas turbines totalling 248 MW nameplate — serving the hyperscale data center on the 335-acre Route 6 property
- files.dep.state.pa.us press
-
2024-12
stagePlanning lodged1 source
- files.dep.state.pa.us press
KDI is submitting this Plan Approval Application (PAA) to the Pennsylvania Department of Environmental Protection (PADEP or Department) in accordance with the Pennsylvania Air Pollution Control Act
- files.dep.state.pa.us press
KDI Wyalusing Power, LLC (KDI) submitted a plan approval (08-00060A) application (Application) to the Pennsylvania Department of Environmental Protection (Department) for the proposed construction and operation of the Wyalusing Energy Center located in Wyalusing Township, Bradford County.
- files.dep.state.pa.us press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.