The Hook Lab / Tracker / North America / United States / Kingston Technology Hub
Updated 2026-11-25
Tracker · United States · US-OTHER · GA
Kingston Technology Hub
Thor Equities · off SR 293, Kingston, Bartow County, GA
Planning lodgedchanged 2026-09
150 MWrequested
—offered
—energised
3 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- off SR 293, Kingston, Bartow County, GA
- Network
- —
- Planning lodged
- 2026-09
- First reported by
- Bisnow · application lodged
- Dates it gives
- DRI filed 2026-09-04
delivery estimated 2030
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-09
stagePlanning lodgedconfirmed
- malachi.energy press
Proposed 350,000 sq ft data center on about 559 acres in the Kingston area of Bartow County, filed for Georgia regional review in September 2026.
- Bisnow press
according to a development of regional impact application filed with the Georgia Department of Community Affairs on Sept. 4.
- malachi.energy press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.