Guild Ventures · Albany, Albany County, NY

Contestedcommunity oppositionstage not on recordchanged 2026-06
180 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
NYISO · NYISO
Place
Albany, Albany County, NY
Network
—
First reported by
rockinst.org · planned

Who is on it

Developer
Guild Ventures · rockinst.org

Timeline

2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-06
    conditionContested1 sourcecommunity opposition
    • rockinst.org press
      Albany residents and advocates protested the project earlier this month, stating concerns over rising utility costs and questioning what community benefits the data center would provide.
  2. 2023-03
    milestoneOwnership changed1 source
    • cbs6albany.com press
      Guild Ventures, who took over the property in March 2023

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.