The Hook Lab / Tracker / North America / United States / Karis Critical Merrillville data centre Updated 2026-11-25
Tracker · United States · IN

Karis Critical Merrillville data centre

Karis Critical · Merrillville (101st Avenue, east of Deep River County Park), IN

Planning approvedchanged 2026-09-14
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
United States · North America
Grid
not settled yet
Place
Merrillville (101st Avenue, east of Deep River County Park), IN
Network
—
Planning approved
2026-09-14
First reported by
GovTech · planned
Dates it gives
plan reported 2024-11

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-09-14date: document dateon or before
    stagePlanning approved1 source
    • DCD press
      The Merrillville Town Council voted 7-0 Tuesday to approve zoning that would allow a data center to be built at the site.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.