The Hook Lab / Tracker / North America / United States / IREN Sweetwater Updated 2026-11-25
Tracker · United States · TX

IREN Sweetwater

IREN · West Texas, TX

Energisingchanged 2026-05-06
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
West Texas, TX
Network
—
Connection applied
2024-12-31
First power
2026-05-06
First reported by
IREN · under construction
Dates it gives
substation energisation due 2026 (Sweetwater 1) and 2027 (Sweetwater 2)

Who is on it

Owner
IREN · sec.gov
Developer
IREN · kiankyars.github.io

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-05-06
    stageEnergising1 source
    • DCD press
      The Nasdaq-listed firm this week announced the successful energization of its 1.4GW Sweetwater 1 data center site in Texas.
  2. 2024-12-31
    stageConnection appliedconfirmed
    • sec.gov primary
      As of December 31, 2024 we have paid $11.7 million of connection deposits in full in order to secure 1,400MW of electrical load capacity and allow the utility to connect the project directly to the ERCOT grid.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.