The Hook Lab / Tracker / North America / United States / IREN Sweetwater
Updated 2026-11-25
Tracker · United States · TX
IREN Sweetwater
IREN · West Texas, TX
Energisingchanged 2026-05-06
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- West Texas, TX
- Network
- —
- Connection applied
- 2024-12-31
- First power
- 2026-05-06
- First reported by
- IREN · under construction
- Dates it gives
- substation energisation due 2026 (Sweetwater 1) and 2027 (Sweetwater 2)
Who is on it
- Owner
- IREN · sec.gov
- Developer
- IREN · kiankyars.github.io
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-05-06
stageEnergising1 source
- DCD press
The Nasdaq-listed firm this week announced the successful energization of its 1.4GW Sweetwater 1 data center site in Texas.
- DCD press
-
2024-12-31
stageConnection appliedconfirmed
- sec.gov primary
As of December 31, 2024 we have paid $11.7 million of connection deposits in full in order to secure 1,400MW of electrical load capacity and allow the utility to connect the project directly to the ERCOT grid.
- sec.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.