The Hook Lab / Tracker / North America / United States / Imperial Data Center Updated 2026-11-25
Tracker · United States · CA

Imperial Data Center

Imperial Valley Computer Manufacturing · unincorporated Imperial County beside the city of Imperial, CA

Contestedplanning approvalstage not on recordchanged 2026-04-08
330 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
unincorporated Imperial County beside the city of Imperial, CA
Network
—
First reported by
inewsource.org · contested
Dates it gives
county approved lot merger 2026-04-07
county moratorium 2026-06

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-04-08date: document dateon or before
    conditionContestedconfirmedplanning approval
    • inewsource.org press
      The city of Imperial has sued Imperial County, challenging ministerial approval of the massive project, the first hyperscale data center in the county.
    • calmatters.org press
      This year the City of Imperial filed a lawsuit challenging the data center’s review under the California Environmental Quality Act, known as CEQA.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.