The Hook Lab / Tracker / North America / United States / Hillwood Spalding County data centre Updated 2026-11-25
Tracker · United States · US-OTHER · GA

Hillwood Spalding County data centre

Hillwood · Spalding County, GA

Planning lodgedchanged 2026-01
—requested
—offered
—energised
11 mowaiting since first filing
lowconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Spalding County, GA
Network
—
Planning lodged
2026-01
First reported by
Bisnow · application lodged
Dates it gives
plans filed 2026-01

Who is on it

Developer
Hillwood · bisnow.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-01
    stagePlanning lodged1 source
    • Bisnow press
      In January, a subsidiary of Hillwood filed plans to develop a 2.2M SF project in Spalding County

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error