Hayward Exchange @ 92
Hines · Hayward, CA
Energisedchanged 2026-08-21
49 MWrequested
—offered
—energised
—closed
highconfidence · 3 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Hayward, CA
- Network
- —
- Planning approved
- 2021-02-11
- First power
- 2026-08-21
- First reported by
- hayward-ca.gov · operating
- Dates it gives
- planning commission approved 2021-02-11
Timeline
20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
- ≤ 2026-08-21date: document dateon or before
-
2021-02-11
stagePlanning approvedconfirmed
- hayward-ca.gov primary
On February 11, 2021, the Planning Commission approved Major Site Plan Review and Conditional Use Permit Application 201906718 for an industrial campus with a data center and three speculative industrial buildings for Hines.
- hayward-ca.gov primary
On February 11, 2021, the Planning Commission approved Major Site Plan Review and Conditional Use Permit Application 201906718 for an industrial campus with a data center and three speculative industrial buildings for Hines.
- hayward-ca.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.