The Hook Lab / Tracker / North America / United States / GW Ranch
Updated 2026-11-25
Tracker · United States · ERCOT · TX
GW Ranch
Pacifico Energy · Pecos County, TX
Planning approvedchanged 2026-08-27
—requested
—offered
—energised
3 mowaiting since first filing
highconfidence · 6 sources
- Market
- United States · North America
- Grid
- ERCOT · ERCOT
- Place
- Pecos County, TX
- Network
- —
- Announced
- 2025-08
- Planning lodged
- 2026-08-27
- Planning approved
- 2026-08-27
- Planning lodged → approved
- 0 mo
- First reported by
- energytech.com · approved
- Dates it gives
- announced 2025-08-20
TCEQ air permit reported 2026-01-28
Who is on it
- Developer
- Pacifico Energy · energytech.com
- Owner
- Amazon · enr.com
- Developer
- Pacifico Energy Group · enr.com
- Architect
- Gensler · enr.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-08-27date: document dateon or before
stagePlanning lodged1 source
- enr.com press
In August, Amazon filed building permits for three 189,000-sq-ft data center buildings to be located on the 8,000-acre remote Pecos County campus, according to energy market and data center research firm Cleanview Inc, which said it matched satellite images and existing state data and received confirmation from the tech firm.
- enr.com press
-
≤ 2026-08-27date: document dateon or before
milestoneOwnership changed1 source
- enr.com press
Tech giant Amazon has confirmed its acquisition of GW Ranch, a massive west Texas hyperscale data center campus that, while touting its low impact on the state’s electrical and water resources, also has the potential of substantial long-term carbon emissions.
- enr.com press
-
≤ 2026-08-27date: document dateon or before
stagePlanning approvedconfirmed
- enr.com press
The project, being developed by California-based Pacifico Energy Group, also has state permits for its campus to build 35 natural gas turbines that can generate up to 7.65 GW of its own power, with plans also for up to 750 MW of on-site solar and 1.8 GW of battery storage capacity.
- energytech.com press
Developer Pacifico Energy announced it has received air permitting approval for the GW Ranch project from the Texas Commission on Environmental Quality.
- pacificoenergy.com primary
The project has received approval from Texas Commission on Environmental Quality (TCEQ), for its air permit of up to 7.65 GW of power generation utilizing a mix of small and large-scale gas turbines.
- enr.com press
-
2025-08
stageAnnounced1 source
- energytech.com press
“GW Ranch isn’t just about scale—it’s about certainty,” said Constantyn Gieskes, vice president at Pacifico Energy, said when the project was announced last August.
- energytech.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.