2025-08
Planning lodged
2026-08-27
Planning approved
2026-08-27
Planning lodged → approved
0 mo
First reported by
energytech.com · approved
Dates it gives
announced 2025-08-20
TCEQ air permit reported 2026-01-28

Who is on it

Developer
Pacifico Energy · energytech.com
Owner
Amazon · enr.com
Developer
Pacifico Energy Group · enr.com
Architect
Gensler · enr.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-08-27date: document dateon or before
    stagePlanning lodged1 source
    • enr.com press
      In August, Amazon filed building permits for three 189,000-sq-ft data center buildings to be located on the 8,000-acre remote Pecos County campus, according to energy market and data center research firm Cleanview Inc, which said it matched satellite images and existing state data and received confirmation from the tech firm.
  2. ≤ 2026-08-27date: document dateon or before
    milestoneOwnership changed1 source
    • enr.com press
      Tech giant Amazon has confirmed its acquisition of GW Ranch, a massive west Texas hyperscale data center campus that, while touting its low impact on the state’s electrical and water resources, also has the potential of substantial long-term carbon emissions.
  3. ≤ 2026-08-27date: document dateon or before
    stagePlanning approvedconfirmed
    • enr.com press
      The project, being developed by California-based Pacifico Energy Group, also has state permits for its campus to build 35 natural gas turbines that can generate up to 7.65 GW of its own power, with plans also for up to 750 MW of on-site solar and 1.8 GW of battery storage capacity.
    • energytech.com press
      Developer Pacifico Energy announced it has received air permitting approval for the GW Ranch project from the Texas Commission on Environmental Quality.
    • pacificoenergy.com primary
      The project has received approval from Texas Commission on Environmental Quality (TCEQ), for its air permit of up to 7.65 GW of power generation utilizing a mix of small and large-scale gas turbines.
  4. 2025-08
    stageAnnounced1 source
    • energytech.com press
      “GW Ranch isn’t just about scale—it’s about certainty,” said Constantyn Gieskes, vice president at Pacifico Energy, said when the project was announced last August.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.