The Hook Lab / Tracker / North America / United States / Google Becker data centre Updated 2026-11-25
Tracker · United States · MISO · MN

Google Becker data centre

Google · Becker, MN

AnnouncedCancelledwithdrawn by proponentchanged 2022-12-21
—requested
—offered
—energised
—closed
mediumconfidence · 2 sources
Market
United States · North America
Grid
MISO · MISO
Place
Becker, MN
Network
—
Announced
2019-12-31
First reported by
Star Tribune · cancelled
Dates it gives
announced about 2020 at 600 million dollars
Google pulled out 2022

Timeline

201820202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2022-12-21date: document dateon or before
    conditionCancelled1 sourcewithdrawn by proponent
    • mprnews.org press
      Tech giant Google is no longer moving forward with plans to build a data center in the central Minnesota city of Becker.
  2. ≤ 2019-12-31on or before
    stageAnnounced1 source
    • mprnews.org press
      In 2019, Xcel revealed it was negotiating with Google to build a 375,000-square-foot data center on roughly 300 acres owned by Xcel Energy

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error