The Hook Lab / Tracker / North America / United States / Galaxy Helios campus
Updated 2026-11-25
Tracker · United States · TX
Galaxy Helios campus
Galaxy Digital · Dickens County, TX
Under constructionchanged 2026-01-15
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Dickens County, TX
- Network
- —
- Connection offered
- 2026-01-15
- Construction started
- 2025-09
- First reported by
- sec.gov · under construction
- Dates it gives
- ERCOT approved a further 830 MW 2026-01
first 133 MW IT due 2026-H1
Who is on it
- Owner
- Galaxy Digital · sec.gov
- Tenant
- CoreWeave · sec.gov
- Financier
- Deutsche Bank AG · sec.gov
- Operator
- Galaxy Digital · usdatamap.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-01-15
stageConnection offeredconfirmed
- sec.gov primary
On January 15, 2026 Galaxy announced the completion of ERCOT Interconnection Studies and the approval for additional 830 MW at Helios.
- sec.gov primary
-
2025-09
stageUnder constructionconfirmed
- sec.gov primary
Galaxy’s Helios Data Center campus under construction for Phase I, September 2025.
- sec.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.