Fort Meade data centre campus
Stonebridge · Fort Meade, Polk County, FL
Planning approvedContestedcommunity oppositionchanged 2026-02-16
1,000 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 4 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- Fort Meade, Polk County, FL
- Network
- —
- Planning approved
- 2025-12-31
- First reported by
- wusf.org · approved
- Dates it gives
- rezoning approved 2025-06
Who is on it
- Developer
- Stonebridge · wusf.org
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-02-16date: document dateon or before
conditionContestedconfirmedcommunity opposition
- wusf.org press
Fort Meade residents spoke against the data center at a public forum last month.
- globaldatacenters.net press
a residents' group has sued the city over its approval
- wusf.org press
-
≤ 2025-12-31on or before
stagePlanning approvedconfirmed
- globaldatacenters.net press
Fort Meade approved the rezoning and a tax break in 2025 and unanimously approved the development agreement in April 2026.
- wusf.org press
The city already approved rezoning and a tax break for the facility last year.
- globaldatacenters.net press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.