Planning approvedchanged 2025-09-23
700 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Minooka, IL
- Network
- —
- Planning approved
- 2025-09-23
- First reported by
- Edison Electric Institute · planned
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-09-23
stagePlanning approved1 source
- datacenterwatch.info press
The project — 4 hyperscale buildings and 3 colocation/retail data centers — was formally approved by the Village of Minooka on September 23, 2025 via annexation, rezoning, and PUD ordinances.
- datacenterwatch.info press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.