Entrata Data Center
Clean Cloud Energy · White Hills, Mohave County, AZ
Planning lodgedchanged 2025-12-16
1,250 MWrequested
—offered
—energised
≥ 11 mowaiting since first filing
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- White Hills, Mohave County, AZ
- Network
- —
- Planning lodged
- 2025-12-16
- First reported by
- azbex.com · application lodged
- Dates it gives
- development start planned 2027 or 2028
Who is on it
- Developer
- Clean Cloud Energy · azbex.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-12-16date: document dateon or before
stagePlanning lodgedconfirmed
- azbex.com press
as it has already submitted a preliminary site plan application
- mahometdaily.com press
By then, Entrata’s team had already filed a preliminary site plan, and county staff said the project could be exempt.
- azbex.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.