DX Hammond · Hammond, former State Line plant site, IN

stage not on recordchanged 2021-07
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
United States · North America
Grid
not settled yet
Place
Hammond, former State Line plant site, IN
Network
—
First reported by
GovTech · operating · opened 2020
Dates it gives
completed 2020-11
bought by DX Hammond 2021-07
full by early 2024

Who is on it

Owner
DX Hammond · govtech.com

Timeline

20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2021-07
    milestoneOwnership changed1 source
    • GovTech press
      DX Hammond purchased the Hammond Data Center in July of 2021, and purchased expansion land on the Digital Crossroads Campus in 2022 and 2023.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.