The Hook Lab / Tracker / Asia / Malaysia / DayOne Tanjung Kupang / Gerbang Nusajaya site Updated 2026-11-25
Tracker · Malaysia · TNB · Johor

DayOne Tanjung Kupang / Gerbang Nusajaya site

DayOne Data Centers Malaysia III Sdn Bhd · Tanjung Kupang, Gerbang Nusajaya, Iskandar Puteri (65 acres), Johor

Application lodged
—planned
—live
1source
Market
Malaysia · Asia
Grid
TNB · TNB (Peninsular Malaysia)
Place
Tanjung Kupang, Gerbang Nusajaya, Iskandar Puteri (65 acres), Johor
Owner
DayOne Data Centers Malaysia III Sdn Bhd
Dates the source gives
Conditional SPA 2026-06 (RM398.1m)
completion expected H2 2027
Source
W.Media

From its first public source so far, linked above, with the dates that source gives. Each step found in registers, filings and the press is added here with its source and the quote it rests on.

Report an error