The Hook Lab / Tracker / North America / United States / CyrusOne Sterling NVA9 Updated 2026-11-25
Tracker · United States · PJM · VA

CyrusOne Sterling NVA9

CyrusOne · Sterling, VA

stage not on recordchanged 2018-07-10
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
PJM · PJM
Place
Sterling, VA
Network
—
First reported by
CyrusOne · operating

Timeline

201820202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2018-07-10
    milestoneOwnership changedconfirmed
    • sec.gov primary
      On July 10, 2018, we acquired 10 acres of land and a newly-built, unoccupied and powered shell for an enterprise data center in Sterling, Virginia for cash consideration of $26.2 million.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error