The Hook Lab / Tracker / North America / United States / Crusoe Childress campus Updated 2026-11-25
Tracker · United States · TX

Crusoe Childress campus

Crusoe · Childress, Childress County, TX

Announcedchanged 2026-07-15
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
not settled yet
Place
Childress, Childress County, TX
Network
—
Announced
2026-07-15
First reported by
Crusoe · planned
Dates it gives
announced 2026-07-15
construction expected 2026-Q3

Who is on it

Operator
Crusoe · crusoe.ai
Developer
Crusoe Energy Systems · datacenterplanet.com
Tenant
Meta · datacenterplanet.com
Developer
Crusoe · cleanview.co

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-07-15
    stageAnnouncedconfirmed
    • Crusoe primary
      Crusoe, the industry's first vertically integrated AI infrastructure provider, and Lancium, an energy technology and infrastructure company, today announced a 1.0 gigawatt (GW) AI data center campus in Childress, Texas.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error