Crossroads Technology Campus
Kettler · Lee Hill area, Spotsylvania County, VA
Contestedcommunity oppositionstage not on recordchanged 2026-07
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Lee Hill area, Spotsylvania County, VA
- Network
- —
- First reported by
- wjla.com · application lodged
- Dates it gives
- planning commission recommended the SUP 4-2, reported 2026-09-21
board vote pending
Who is on it
- Network operator
- Dominion Energy · datacentercensus.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-07
conditionContestedconfirmedcommunity opposition
- datacentercensus.com press
Residents pack Board of Supervisors and Planning Commission meetings to challenge the project
- wjla.com press
Since then, those residents have been fighting to stop – or at the very least improve - the project because of concerns about their home values, noise, and environmental impacts.
- datacentercensus.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.