The Hook Lab / Tracker / North America / United States / Crooked Creek data centre Updated 2026-11-25
Tracker · United States · MO

Crooked Creek data centre

Beltline Energy · Franklin County, MO

Planning lodgedchanged 2026-01-28
—requested
—offered
—energised
10 mowaiting since first filing
mediumconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
Franklin County, MO
Network
—
Announced
2026-01-27
Planning lodged
2026-01-28
First reported by
spectrumlocalnews.com · contested
Dates it gives
lawsuits reported 2026-10-15

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-01-28date: document dateon or before
    stagePlanning lodged1 source
    • stlmag.com press
      An official planned use development application has been submitted to the city.
  2. 2026-01-27
    stageAnnounced1 source
    • stlmag.com press
      Tuesday’s meeting focused entirely on a presentation from Atlanta-based Beltline Energy that outlined the developer’s proposal to build up to 16 new buildings, representing up to a $16 billion total investment, on land they want Pacific to annex from an unincorporated part of Franklin County.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error