The Hook Lab / Tracker / North America / United States / CRG St. Charles data centre
Updated 2026-11-25
Tracker · United States · MO
CRG St. Charles data centre
CRG · St. Charles, MO
Contestedcommunity oppositionstage not on recordchanged 2025-08-19
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
- Market
- United States · North America
- Grid
- not settled yet
- Place
- St. Charles, MO
- Network
- —
- First reported by
- stlmag.com · cancelled
Who is on it
- Developer
- CRG · stlmag.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2025-08-19date: document dateon or before
conditionContested1 sourcecommunity opposition
- GovTech press
On Sunday, a citizen’s group called for an investigation into efforts to bring the data center to north St. Charles near Highway 370, citing a lack of transparency on the project, concerns over environmental impacts and the mayor’s relationship to the landowner, Clarice Hollrah, who is a cousin of Borgmeyer.
- GovTech press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.