CoreWeave Lancaster data centre
CoreWeave · Lancaster, Lancaster County, PA
Announcedchanged 2025-07-15
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Lancaster, Lancaster County, PA
- Network
- —
- Announced
- 2025-07-15
- First reported by
- CoreWeave · planned
- Dates it gives
- announced 2025-07-15
Who is on it
- Tenant
- CoreWeave · coreweave.com
- Developer
- Chirisa Technology Parks · datacenterdynamics.com
- Developer
- Machine Investment Group · datacenterdynamics.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-07-15
stageAnnouncedconfirmed
- DCD press
AI cloud firm CoreWeave has revealed plans to invest up to $6 billion in developing a data center in Lancaster, Pennsylvania.
- CoreWeave primary
today announced its intent to commit more than $6 billion to equip a new, state-of-the-art data center in Lancaster, Pennsylvania, purpose-built to power the most cutting-edge AI use cases.
- DCD press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.