The Hook Lab / Tracker / North America / United States / Core Scientific Marble Updated 2026-11-25
Tracker · United States · US-OTHER · NC

Core Scientific Marble

Core Scientific · Marble, NC

stage not on recordchanged 2017-12-31
65 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Marble, NC
Network
—
First reported by
Core Scientific · operating

Who is on it

Operator
Core Scientific · suedatacenters.org
Developer
Core Scientific · cleanview.co

Timeline

2016201820202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2017-12-31on or before
    milestoneOwnership changedconfirmed
    • sec.gov primary
      Purchased first data center in Marble, NC

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.