The Hook Lab / Tracker / North America / United States / Core Scientific Denton
Updated 2026-11-25
Tracker · United States · ERCOT · TX
Core Scientific Denton
Core Scientific · Denton, TX
Announcedchanged 2024-06
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
- Market
- United States · North America
- Grid
- ERCOT · ERCOT
- Place
- Denton, TX
- Network
- —
- Announced
- 2021-10
- First reported by
- Core Scientific · operating
Who is on it
- Developer
- Tenaska Energy, Inc. · sec.gov
- Owner
- Core Scientific · datacenterdynamics.com
Timeline
20202022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2024-06
milestoneconfirmed
- sec.gov primary
Core Scientific completed a 72 MW infrastructure expansion project at its Denton, Texas data center, increasing its total operational infrastructure to 832 MW.
- sec.gov primary
-
2021-10
stageAnnouncedconfirmed
- sec.gov primary
In addition, in October 2021, we announced the entry of an agreement with the City of Denton, Texas and an affiliate of Tenaska Energy, Inc. to develop our seventh facility, a blockchain data center in Denton, Texas
- sec.gov primary
today announced an agreement with the City of Denton, Texas and an affiliate of Tenaska Energy, Inc. to develop a 300MW blockchain data center in Denton, using emissions-free power supplemented by renewable energy credits.
- sec.gov primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.