The Hook Lab / Tracker / North America / United States / Constant Company Springfield data centre Updated 2026-11-25
Tracker · United States · PJM · OH

Constant Company Springfield data centre

The Constant Company · Springfield, OH

Announcedchanged 2025-10-30
—requested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
United States · North America
Grid
PJM · PJM
Place
Springfield, OH
Network
—
Announced
2025-10-30
First reported by
whio.com · planned
Dates it gives
state data-centre tax exemption approved 2025-10

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2025-10-30date: document dateon or before
    stageAnnounced1 source
    • springfieldnewssun.com press
      Ohio Gov. Mike DeWine announced the project along with 11 others across the state, as part of 1,200 new jobs in Ohio.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error