The Hook Lab / Tracker / North America / United States / Compass Meridian campus Updated 2026-11-25
Tracker · United States · US-OTHER · MS

Compass Meridian campus

Compass Datacenters · Meridian, MS

Under constructionchanged 2025-12-31
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
Meridian, MS
Network
—
Construction started
2025-12-31
First reported by
Compass · under construction
Dates it gives
broke ground 2025

Who is on it

Operator
Compass Datacenters · usdatamap.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2025-12-31on or before
    stageUnder constructionconfirmed
    • Compass primary
      Meridian broke ground in 2025, 80 miles east of Jackson, this 320 MW site is set to become one of the largest data center campuses in the Southeast.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.