The Hook Lab / Tracker / North America / United States / Chesapeake Great Bridge data centre Updated 2026-11-25
Tracker · United States · PJM · VA

Chesapeake Great Bridge data centre

Doug Fuller · Ethridge Manor Boulevard and Centerville Turnpike, Great Bridge, Chesapeake, VA

Connection offeredchanged 2025-05-13
—requested
—offered
—energised
18 mowaiting since first filing
mediumconfidence · 2 sources
Market
United States · North America
Grid
PJM · PJM
Place
Ethridge Manor Boulevard and Centerville Turnpike, Great Bridge, Chesapeake, VA
Network
—
Planning lodged
2025-05-13
Connection offered
2024-12-31
First reported by
whro.org · application lodged
Dates it gives
Dominion confirmed up to 200 MW late summer 2024
planning commission 2025-05-14

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2025-05-13date: document dateon or before
    stagePlanning lodged1 source
    • whro.org press
      A Chesapeake developer has filed plans to build the first large-scale data center in Hampton Roads.
  2. ≤ 2024-12-31on or before
    stageConnection offered1 source
    • whro.org press
      Late last summer, Fuller and his partner got confirmation from Dominion that they would be able to draw the necessary power from the neighboring substation – up to 200 megawatts, though he said the data center won’t need nearly that much.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.