Calvert Infrastructure Hub
Beacon Data Centers · Mobile County, AL
Announcedchanged 2026-06-30
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- Mobile County, AL
- Network
- —
- Announced
- 2026-06-30
- First reported by
- W.Media · planned
- Dates it gives
- first building due 2027 (as of 2026-07)
Who is on it
- Network operator
- Alabama Power · beacondatacenters.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-06-30date: document dateon or before
stageAnnouncedconfirmed
- beacondatacenters.com primary
Calvert Infrastructure Hub is a next-generation data center development planned in Calvert, Alabama.
- beacondatacenters.com primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.