The Hook Lab / Tracker / North America / United States / AVAIO Project Leo Updated 2026-11-25
Tracker · United States · MISO · AR

AVAIO Project Leo

AVAIO Digital Partners · south of Little Rock, Pulaski County, AR

Planning approvedchanged 2026-08-25
1,000 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 3 sources
Market
United States · North America
Grid
MISO · MISO
Place
south of Little Rock, Pulaski County, AR
Network
—
Announced
2026-01-12
Planning approved
2026-08-25
First reported by
talkbusiness.net · connection offered
Dates it gives
announced 2026-01
expected to open 2027-06

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-08-25date: document dateon or before
    stagePlanning approved1 source
    • avaiodigital.com press
      The site, less than ten miles from downtown Little Rock, has a fully approved Site Plan with substantial existing on-site water and sewer infrastructure:
  2. 2026-01-12
    stageAnnounced1 source
    • avaiodigital.com press
      UPDATE (January 12, 2026): AVAIO Digital Announces New Large-Scale AI-Ready Data Center and Power Campus in Little Rock, Arkansas
    • avaiodigital.com press
      AVAIO Digital Partners (AVAIO Digital) announced today a major new data center hub near Little Rock in Pulaski County, Arkansas – AVAIO Digital Leo – that will help accelerate the state’s rapidly growing tech sector.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.