The Hook Lab / Tracker / North America / United States / Atlas Agro Benton County data centre campus Updated 2026-11-25
Tracker · United States · US-OTHER · WA

Atlas Agro Benton County data centre campus

Atlas Agro · adjacent to the Northwest Advanced Clean Energy Park, Benton County, WA

Announcedchanged 2025-12
320 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
United States · North America
Grid
US-OTHER · Other US (outside the ISOs)
Place
adjacent to the Northwest Advanced Clean Energy Park, Benton County, WA
Network
—
Announced
2025-12
First reported by
columbiariverkeeper.org · planned
Dates it gives
report dated 2026-02-26

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2025-12
    stageAnnounced1 source
    • isadatacentercoming.com press
      Zero carbon fertilizer company Atlas Agro wants to build five data center buildings of about 500,000 square feet each, a 500 million dollar project, on 275 acres at 2100 Horn Rapids Road next to its planned 1.5 billion dollar Richland fertilizer plant in the Northwest Advanced Clean Energy Park.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.

Report an error