The Hook Lab / Tracker / North America / United States / Armory Innovation District data centre Updated 2026-11-25
Tracker · United States · MO

Armory Innovation District data centre

TerraWatt · Midtown St. Louis (former Famous-Barr warehouse, Market Street, near the Armory), MO

Planning approvedContestedplanning approvalchanged 2026-09-17
120 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 3 sources
Market
United States · North America
Grid
not settled yet
Place
Midtown St. Louis (former Famous-Barr warehouse, Market Street, near the Armory), MO
Network
—
Announced
2026-01-16
Planning approved
2026-04-21
First reported by
stlpr.org · contested
Dates it gives
final city approval 2026-04 and board ruling 2026-07 (STLPR headlines)
lawsuits filed 2026-09

Who is on it

Developer
TerraWatt · stlmag.com
Developer
Contour · stlmag.com
Developer
Steadfast City · stlmag.com
Developer
THO Investments · stlmag.com
Developer
ARCO · stlmag.com
Developer
Lewis Rice · stlpr.org

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-09-17date: document dateon or before
    conditionContested1 sourceplanning approval
    • stlpr.org press
      Lambiaso and the City of St. Louis are also being sued over the project by the Missouri Coalition for the Environment and several other plaintiffs who argue that the city illegally granted a use permit for the project.
  2. 2026-04-21
    stagePlanning approved1 source
    • stlmag.com press
      A major data center development in St. Louis’ Midtown neighborhood is moving forward now that the Board of Public Service signed off on a conditional use permit for the project on Tuesday afternoon.
  3. ≤ 2026-01-16date: document dateon or before
    stageAnnounced1 source
    • stlpr.org press
      The developers behind the Armory data center announced a new plan Friday for the space.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.