The Hook Lab / Tracker / North America / United States / Armory Innovation District data centre
Updated 2026-11-25
Tracker · United States · MO
Armory Innovation District data centre
TerraWatt · Midtown St. Louis (former Famous-Barr warehouse, Market Street, near the Armory), MO
Planning approvedContestedplanning approvalchanged 2026-09-17
120 MWrequested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 3 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Midtown St. Louis (former Famous-Barr warehouse, Market Street, near the Armory), MO
- Network
- —
- Announced
- 2026-01-16
- Planning approved
- 2026-04-21
- First reported by
- stlpr.org · contested
- Dates it gives
- final city approval 2026-04 and board ruling 2026-07 (STLPR headlines)
lawsuits filed 2026-09
Who is on it
- Developer
- TerraWatt · stlmag.com
- Developer
- Contour · stlmag.com
- Developer
- Steadfast City · stlmag.com
- Developer
- THO Investments · stlmag.com
- Developer
- ARCO · stlmag.com
- Developer
- Lewis Rice · stlpr.org
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-09-17date: document dateon or before
conditionContested1 sourceplanning approval
- stlpr.org press
Lambiaso and the City of St. Louis are also being sued over the project by the Missouri Coalition for the Environment and several other plaintiffs who argue that the city illegally granted a use permit for the project.
- stlpr.org press
-
2026-04-21
stagePlanning approved1 source
- stlmag.com press
A major data center development in St. Louis’ Midtown neighborhood is moving forward now that the Board of Public Service signed off on a conditional use permit for the project on Tuesday afternoon.
- stlmag.com press
-
≤ 2026-01-16date: document dateon or before
stageAnnounced1 source
- stlpr.org press
The developers behind the Armory data center announced a new plan Friday for the space.
- stlpr.org press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.