Announcedchanged 2026-07-27
430 MWrequested
—offered
—energised
—waiting: no filing date on record
lowconfidence · 1 source
Market
United States · North America
Grid
not settled yet
Place
near Toronto, Deuel County, SD
Network
—
Announced
2026-07-27
First reported by
kfgo.com · paused
Dates it gives
state incentives rejected 2026

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. ≤ 2026-07-27date: document dateon or before
    stageAnnounced1 source
    • DCD press
      First reported by Dakota News Now, the data center operator is proposing an AI data center development east of Toronto in South Dakota.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.