The Hook Lab / Tracker / North America / United States / Applied Digital Polaris Forge 2 Updated 2026-11-25
Tracker · United States · ND

Applied Digital Polaris Forge 2

Applied Digital · Harwood, ND

Under constructionchanged 2025-08-18
—requested
—offered
—energised
—waiting: no filing date on record
highconfidence · 3 sources
Market
United States · North America
Grid
not settled yet
Place
Harwood, ND
Network
—
Announced
2025-08-18
Construction started
2025-08-18
First reported by
Applied Digital · under construction
Dates it gives
initial operations expected by end of 2026

Who is on it

Owner
Applied Digital · sec.gov

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2025-08-18
    stageAnnouncedconfirmed
    • sec.gov primary
      On August 18, 2025, we also announced that we would be breaking ground on our Polaris Forge 2 campus, a $3 billion, 280 MW data center near Harwood, North Dakota.
    • Applied Digital primary
      Applied Digital Corporation (Nasdaq: APLD) announced today it plans to break ground in September 2025 on Polaris Forge 2, a $3 billion, 280-megawatt (MW) AI Factory near Harwood, North Dakota.
  2. 2025-08-18
    stageUnder constructionconfirmed
    • sec.gov primary
      On August 18, 2025, we broke ground on Polaris Forge 2, a $3 billion, 200 MW data center campus near Harwood, North Dakota.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.