The Hook Lab / Tracker / North America / United States / Applied Digital Polaris Forge 1 Updated 2026-11-25
Tracker · United States · ND

Applied Digital Polaris Forge 1

Applied Digital · Ellendale, ND

Energisedchanged 2026-07-01
—requested
—offered
—energised
—closed
highconfidence · 2 sources
Market
United States · North America
Grid
not settled yet
Place
Ellendale, ND
Network
—
First power
2025-10
First reported by
Applied Digital · operating · opened 2025
Dates it gives
first 100 MW building operational October 2025
Building 2 ready for service 2026-07-01 (75 MW) and 2026-10-01 (75 MW)

Who is on it

Tenant
CoreWeave · ir.applieddigital.com
Owner
Applied Digital · sec.gov
Operator
Applied Digital · ir.applieddigital.com

Timeline

202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today

History

  1. 2026-07-01
    milestoneExpandedconfirmed
    • Applied Digital primary
      today announced it has achieved Ready for Service for Phase 1 of Building 2 at Polaris Forge 1, delivering 75 MW of operational AI capacity to its customer on schedule and bringing total live capacity at the campus to 175 MW.
  2. 2025-10
    stageEnergisedconfirmed
    • Applied Digital primary
      The first 100 MW building at Polaris Forge 1 became operational in October 2025.

Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.