Applied Digital Polaris Forge 1
Applied Digital · Ellendale, ND
Energisedchanged 2026-07-01
—requested
—offered
—energised
—closed
highconfidence · 2 sources
- Market
- United States · North America
- Grid
- not settled yet
- Place
- Ellendale, ND
- Network
- —
- First power
- 2025-10
- First reported by
- Applied Digital · operating · opened 2025
- Dates it gives
- first 100 MW building operational October 2025
Building 2 ready for service 2026-07-01 (75 MW) and 2026-10-01 (75 MW)
Who is on it
- Tenant
- CoreWeave · ir.applieddigital.com
- Owner
- Applied Digital · sec.gov
- Operator
- Applied Digital · ir.applieddigital.com
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2026-07-01
milestoneconfirmed
- Applied Digital primary
today announced it has achieved Ready for Service for Phase 1 of Building 2 at Polaris Forge 1, delivering 75 MW of operational AI capacity to its customer on schedule and bringing total live capacity at the campus to 175 MW.
- Applied Digital primary
-
2025-10
stageEnergisedconfirmed
- Applied Digital primary
The first 100 MW building at Polaris Forge 1 became operational in October 2025.
- Applied Digital primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.