Amazon Web Services Butts County data centres
Amazon Web Services · Butts County, GA
Announcedchanged 2025-01-07
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- US-OTHER · Other US (outside the ISOs)
- Place
- Butts County, GA
- Network
- —
- Announced
- 2025-01-07
- First reported by
- Amazon · planned
- Dates it gives
- announced 2025-02-21
Who is on it
- Operator
- Amazon Web Services · suedatacenters.org
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2025-01-07
stageAnnouncedconfirmed
- datacentercensus.com press
AWS announces at least $11 billion investment in Butts and Douglas counties
- suedatacenters.org press
AWS announced at least $11B of new data center capacity in Georgia, naming Butts and Douglas counties.
- datacentercensus.com press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.