The Hook Lab / Tracker / North America / United States / Amazon Summit Crossing Tech Campus
Updated 2026-11-25
Tracker · United States · PJM · VA
Amazon Summit Crossing Tech Campus
Amazon Web Services · Spotsylvania County, VA
Planning approvedchanged 2023-10
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 2 sources
- Market
- United States · North America
- Grid
- PJM · PJM
- Place
- Spotsylvania County, VA
- Network
- —
- Planning approved
- 2023-10
- First reported by
- DCD · approved
- Dates it gives
- filed 2023-06
Timeline
2022202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
2023-10
stagePlanning approvedconfirmed
- suedatacenters.org press
Board of Supervisors approved the rezoning on a 5-2 vote (Oct 2023).
- DCD press
All four – the Summit Crossing Tech Campus, Carter’s Store Tech Campus, Cosner Tech Campus, and the Orrock Tech Campus – have since received zoning approval.
- suedatacenters.org press
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.