The Hook Lab / Tracker / North America / United States / Amazon Hinds County data centres
Updated 2026-11-25
Tracker · United States · MISO · MS
Amazon Hinds County data centres
Amazon Web Services · Hinds County, MS
Announcedchanged 2026-04-09
—requested
—offered
—energised
—waiting: no filing date on record
mediumconfidence · 1 source
- Market
- United States · North America
- Grid
- MISO · MISO
- Place
- Hinds County, MS
- Network
- —
- Announced
- 2026-04-09
- First reported by
- Amazon · planned
- Dates it gives
- announced 2026-04-09
Who is on it
- Operator
- Amazon Web Services · suedatacenters.org
Timeline
202420262028
before a connection offeroffer to powerpower ondelayed, paused, contested╷ milestone│ today
History
-
≤ 2026-04-09date: document dateon or before
stageAnnouncedconfirmed
- Amazon primary
a $1 billion investment in Hinds County, where we are transforming the former Delphi manufacturing plant into a cutting-edge data center facility.
- Amazon primary
Newest first. Every step shows the source and the quote it rests on, checked against that source. Confirmed: a primary source (a register, a filing, the owner's own site) or two sites; a cancellation needs both. 1 source: one so far. Only confirmed dates enter medians and comparables. A stage is how far the project has got; a condition (delayed, contested, paused, cancelled) sits on top of the stage until a later event ends it. Unknown fields show as —.